The last day of the 13th week. Work continues on the roof, the chimneys, the chapel floor and paintwork, the re-pointing and the cellar floor and internal walls.
The internal plasterwork begins to cover over the evidence of earlier fireplaces and alterations to the rear wall facing Jackson Pit.
The gable wall to David Street starts to look like a proper internal wall again.
First coat of plaster. Internal wall at the SW corner of the cellar at the corner of Jackson Pit and David Street, Oldham. |
First coat of plaster. Internal wall, south gable looking towards the corner of David Street and George Street. |
No comments:
Post a Comment