Week 42 - Day 206
New spindles to match original surviving ones that were located around the stairwell from the chapel to the gallery.
Information posted by the Friends of George Street about events and activities at the former Independent Methodist Chapel at George Street, Oldham by Age UK Oldham. The early posts describe the works to conserve, restore and adapt this Grade ll* Listed Building betwee 2012-13. Restoration works were supported by a grant from the HLF, with match funding from the Andrew Lloyd Webber Challenge Fund, English Heritage and the Architectural Heritage Fund as well as Viridor Credits and Lloyds Bank.
Showing posts with label new staircase. Show all posts
Showing posts with label new staircase. Show all posts
Monday, 2 December 2013
Monday, 19 August 2013
Day 132 - New Staircase Starts to be Erected
Week 28 - Day 132
Today the new staircase started to be fitted together providing a link between the basement and the chapel.
Today the new staircase started to be fitted together providing a link between the basement and the chapel.
Friday, 16 August 2013
Thursday, 15 August 2013
Day 130 - New Staircase
Week 27 - Day 130
This is where the new staircase will be fitted tomorrow. To allow access between the basement and the main chapel floor.
This is where the new staircase will be fitted tomorrow. To allow access between the basement and the main chapel floor.
Monday, 1 July 2013
Thursday, 27 June 2013
Day 97 - New Staircase - Joists Removed
Week 21 - Day 97
With the floorboards removed yesterday the floor joists were removed to allow for the new staircase to be constructed.
This opens up a large space in the NW corner of the building allowing light to flood down into new stairwell.
With the floorboards removed yesterday the floor joists were removed to allow for the new staircase to be constructed.
This opens up a large space in the NW corner of the building allowing light to flood down into new stairwell.
Wednesday, 26 June 2013
Day 96 - New Stairwell Starts to be Constructed - Lifting Floorboards
Week 21 - Day 96
A section of the chapel floorboards were lifted today to allow for the construction of the new staircase.
two sets of pews have had to be removed to allow for the stairs to be located in the NW corner of the building
A section of the chapel floorboards were lifted today to allow for the construction of the new staircase.
two sets of pews have had to be removed to allow for the stairs to be located in the NW corner of the building
Monday, 25 February 2013
Day 16 - NW Corner Cleared - location of new staircase