Wednesday, 30 October 2013

Day 183 - Primer Paint to Vestry and Gallery

Week 38 - Day 183
Starting to prime woodwork in the chapel today. The vestry was a later addition within the chapel is is a lower quality wood compared to earlier fitments such as the pews and pulpit.

Undercoat to the woodwork of the vestry.

Preparation of the woodwork to the vestry and the gallery. 

Thursday, 5 September 2013

Day 144 - Former Vestry to Become Kitchen Area

Week 30 - Day 144
The former vestry are in the SE corner of the chapel is getting ready to become the new kitchen area.

Thursday, 22 August 2013

Day 135 - Plastering Works Start in the Old Vestry / New Kitchen

Week 28 - Day 135
The former vestry spaces have started to be converted into their new uses as kitchen and washing -up areas.