Week 40 - Day 191
Wet day again today. The fresh pointing has had to be protected from the wet to stop the lime mortar from washing out and staining the bricks. Probably without time constraints this would have been put off until a drier day, but we are working towards an end date of mid-December.
Information posted by the Friends of George Street about events and activities at the former Independent Methodist Chapel at George Street, Oldham by Age UK Oldham. The early posts describe the works to conserve, restore and adapt this Grade ll* Listed Building betwee 2012-13. Restoration works were supported by a grant from the HLF, with match funding from the Andrew Lloyd Webber Challenge Fund, English Heritage and the Architectural Heritage Fund as well as Viridor Credits and Lloyds Bank.
Showing posts with label pointing. Show all posts
Showing posts with label pointing. Show all posts
Monday, 11 November 2013
Tuesday, 22 October 2013
Day 177 - Removal of Perimeter Fencing and Work to Outer Walls
Week 37 - Day 177
With doors and windows in place the external perimeter fencing as well as the scaffolding is being removed. This opens up the lower sections of the outer walls for repairs and repointing.
With doors and windows in place the external perimeter fencing as well as the scaffolding is being removed. This opens up the lower sections of the outer walls for repairs and repointing.
![]() |
| Removal of the external perimeter fencing from the David Street - George Street side of George Street Chapel, Oldham. |
Location:
Oldham, UK
Monday, 21 October 2013
Day 176 - Finishing off Pointing and Brickwork
Week 37 - Day 176
With all the upper works completed - gutters, windows etc the scaffolding can start to be removed and the pointing works completed where the scaffolding prevented access.
With all the upper works completed - gutters, windows etc the scaffolding can start to be removed and the pointing works completed where the scaffolding prevented access.
![]() |
| Jackson Pit elevation of George Street Chapel as the scaffolding starts to be removed. |
![]() |
| Repairing all the decayed brickwork at the SW corner where lack of maintenance to gutters and downpipes has caused progressive damage to the brickwork. |
Location:
Oldham, UK
Friday, 27 September 2013
Day 160 - Tidying up Walls Around Windows
Week 33 - Day 160
The bricks around the windows were disturbed whilst removing the windows, start made toady to restore the edges. Also to point the courses which couldn't be pointed because the scaffolding was tight against the wall.
The bricks around the windows were disturbed whilst removing the windows, start made toady to restore the edges. Also to point the courses which couldn't be pointed because the scaffolding was tight against the wall.
Tuesday, 2 April 2013
Day 40 - The Start of Repairs and Restoration - Pointing Samples
Week 9 - Day 40
After the Easter break work is edging towards the repair and restoration elements of the project.
The unstable sections at the top of the southern chimney are being taken down, ready for rebuilding.
The northern chimney has already lost its upper section, which will be re-built to match the one at the south end.
Samples of different types of mortar are being used to re-point sections of the brickwork, so that the most appropriate mix can be used.
After the Easter break work is edging towards the repair and restoration elements of the project.
The unstable sections at the top of the southern chimney are being taken down, ready for rebuilding.
The northern chimney has already lost its upper section, which will be re-built to match the one at the south end.
Samples of different types of mortar are being used to re-point sections of the brickwork, so that the most appropriate mix can be used.
![]() |
| The southern chimney at the David Street end of George Street Chapel. |
![]() |
| Sample of pointing and mortar mix at George Street Chapel. |
![]() |
| Sample of pointing and mortar mix at George Street Chapel. |