Friday 29 November 2013

Day 205 - Continuing Preping all the Woodwork

Week 41 - Day 205
Continuing the preparation of all the woodwork.
The stained top rail for the safety rail awaits completion on Monday.
More preparation of the wooden rails in front of the pulpit.



Thursday 28 November 2013

Tuesday 26 November 2013

Day 202 - Cleaning, Stripping, Painting

Week 41 - Day 202
More cleaning, stripping and painting working down from the gallery.


Monday 25 November 2013

Day 201 - Front Steps

Week 41 - Day 201
Original steps with some new stone supported on new bricks and a new rsj.


Saturday 23 November 2013

FOGS Visit to Englesea Brook Chapel and Museum of Primitive Methodism

Today the Friends of George Street visited the Museum of Primitive Methodism at Englesea Brook Chapel, Cheshire.
It was a frosty morning at -3 degrees but we had a warm welcome by Dr Jill Barber the Project Director.
The new wheelchair access constructed at Englesea Brook.
The front door into the chapel with the gallery above. 
View from the pews in the gallery with the pulpit and harmonium. 

Friday 22 November 2013

Day 200 - Fixing the Front Step

Week 40 - Day 200
The supporting structure for the front steps needed completely replacing. The iron bar was corroded. With a new steel girder in place the brickwork to support the stone steps to the front door can now be built up. The stone is ready to be put in place next week.






Thursday 21 November 2013

Day 199 - Cleaning up Floorboards - Vacuuming

Week 40 - Day 199
Extreme vacuum cleaning after cleaning up the chapel floor. The pews are cleaning up nicely as well.


Wednesday 20 November 2013

Day 198 - Washing -up in the Bar Area

Week 40 - Day 198
Starting to put the fittings in place. This is the bar area in the cellar.

Tuesday 19 November 2013

Day 197 - Cleaning up Floorboards

Week 40 - Day 197
The original chapel floorboards have started to be cleaned up. They had been covered over by a lighter coloured maplewood boarding in the 1990s.

Monday 18 November 2013

Day 196 - Access to 58 George Street

Week 40 - Day 196
Though the door into 58, George Street has had to be sealed up (the gents toilets are down there now) the steps from the street are still there and are being tidied up.
The font steps to the chapel still need to be rebuilt above once a new steel support is put in place.


Friday 15 November 2013

Day 195 - Relaying Blocks to Rear

Week 39 - Day 195
At the rear in Jackson Pit the blocks were being relaid today having lifted them, broken up the concrete, laid new drainage and sewerage and made good the ground.


Thursday 14 November 2013

Day 194 - Preparations in the Preparation Areas

Week 40 -Day 194
The old vestry spaces are to be used for food preparation and washing-up areas.
Electrics are being inserted ready for the delivery of appliances.



Wednesday 13 November 2013

Tuesday 12 November 2013

Day 192 - Front Steps

Week 40 - Day 192
The front steps were removed today to be refurbished and to replace the support structure.
the block door way used to be to cellar dwelling with the address 58, George Street. The other three cellars were accessed from Jackson pit at the rear.



Monday 11 November 2013

Day 191 - Pointing in the Rain

Week 40 - Day 191
Wet day again today. The fresh pointing has had to be protected from the wet to stop the lime mortar from washing out and staining the bricks. Probably without time constraints this would have been put off until a drier day, but we are working towards an end date of mid-December.



Friday 8 November 2013

Day 190 - Things Get Worse Before They Get Better

Week 39 - Day 190
You can't get in through the back door now.
The works to connect up the drainage get down to the the connecting phase, unfortunately its been raining again this week!




Thursday 7 November 2013

Day 189 - Front Door

Week 39 - Day 189
Attention moves to the front door.
Repairs to front door of George Street Chapel, Oldham.

Wednesday 6 November 2013

Day 188 - Breaking Ground for Drainage

Week 39 - Day 188
The area below where the cabins stood have been broken up to allow the new drainage services to be put in.





Tuesday 5 November 2013

Day 187 - Site Cabin Removed

Week 39 - Day 187
The site cabin was removed today. Always a sign that the project is coming to an end. But also required because the drainage and sewers need to be connected up.
The site office has been moved up to the gallery level of the chapel.
Removal of site cabin at rear of George Street Chapel,
looking north up Jackson Pit, Oldham.