Week 37 - Day 180
The soldier bricks above the windows are relaid. The new window cills are fitted in below the windows to replace the damages cills.
Information posted by the Friends of George Street about events and activities at the former Independent Methodist Chapel at George Street, Oldham by Age UK Oldham. The early posts describe the works to conserve, restore and adapt this Grade ll* Listed Building betwee 2012-13. Restoration works were supported by a grant from the HLF, with match funding from the Andrew Lloyd Webber Challenge Fund, English Heritage and the Architectural Heritage Fund as well as Viridor Credits and Lloyds Bank.
Showing posts with label windows. Show all posts
Showing posts with label windows. Show all posts
Friday, 25 October 2013
Thursday, 24 October 2013
Day 179 - Sunlight Across the Restoration
Week 37 - Day 179
The sun was doing its thing today after days of rain and cloud. Now the external fencing is down and scaffolding removed the sun can once again shine through the coloured glass.
It should look fabulous when all the surfaces are stained and painted.
The sun was doing its thing today after days of rain and cloud. Now the external fencing is down and scaffolding removed the sun can once again shine through the coloured glass.
It should look fabulous when all the surfaces are stained and painted.
Friday, 27 September 2013
Day 160 - Tidying up Walls Around Windows
Week 33 - Day 160
The bricks around the windows were disturbed whilst removing the windows, start made toady to restore the edges. Also to point the courses which couldn't be pointed because the scaffolding was tight against the wall.
The bricks around the windows were disturbed whilst removing the windows, start made toady to restore the edges. Also to point the courses which couldn't be pointed because the scaffolding was tight against the wall.
Tuesday, 17 September 2013
Friday, 6 September 2013
Day 145 - Windows Replaced behind Organ
Week 30 - Day 145
The windows either side of the organ in the David Street gable on the south side of the chapel were replaced today.
The windows either side of the organ in the David Street gable on the south side of the chapel were replaced today.
![]() |
| George Street Chapel windows replaced in the southern gable, on David Street. |
Friday, 23 August 2013
Day 136 - New Window Painted
Week 28 - Day 136
One of the large chapel windows was too rotten to be saved. These are all replacement windows inserted in the 1990's by the last owner. sadly the original ones with the hopper window openings were not saved, and not reproduced either. A complete re-make of all the windows to the original design was sadly too expensive an option, so the windows have been cleaned, repaired and repainted but one was too poorly preserved and a new one has been made.
One of the large chapel windows was too rotten to be saved. These are all replacement windows inserted in the 1990's by the last owner. sadly the original ones with the hopper window openings were not saved, and not reproduced either. A complete re-make of all the windows to the original design was sadly too expensive an option, so the windows have been cleaned, repaired and repainted but one was too poorly preserved and a new one has been made.
![]() |
| New window replacing one of the ones removed. |
![]() |
| Replaced windows in the basement having been cleaned and renovated. |
Wednesday, 14 August 2013
Day 129 - Roof Lights and Basement Windows
Monday, 12 August 2013
Day 127 - Fitting of New Stone Sills
Labels:
stone sills,
windows
Location:
Oldham, UK
Monday, 10 June 2013
Tuesday, 4 June 2013
Monday, 3 June 2013
Day 80 - Work on Windows
Week 18 - Day 80
With the work to install the ceiling laths now completed, refurbishment of the windows in the temporary roof space has been taken up again. The glass was removed earlier, along with the paint - so now work can be carried out to replace rotten elements of the frames.
With the work to install the ceiling laths now completed, refurbishment of the windows in the temporary roof space has been taken up again. The glass was removed earlier, along with the paint - so now work can be carried out to replace rotten elements of the frames.
Labels:
windows
Location:
Oldham, UK
Wednesday, 15 May 2013
Day 69 - Windows
Week 15 - Day 69
The tops of the windows needed to be reset as the mortar was beginning to fail. The header bricks actually partially support the stone gutter, so need to be well set to support the weight.
The tops of the windows needed to be reset as the mortar was beginning to fail. The header bricks actually partially support the stone gutter, so need to be well set to support the weight.
Wednesday, 27 March 2013
Day 38 - Window Repairs
Wednesday, 6 March 2013
Day 23 - Ladder to Temporary Floor in the Roof
Week 5 - Day 23
The scaffolders completed access to the new temporary floor in the roof.
This is currently being used to work on refurbishing the windows, but will later allow work to proceed on the ceiling, the roof trusses and the roof itself.
The scaffolders completed access to the new temporary floor in the roof.
This is currently being used to work on refurbishing the windows, but will later allow work to proceed on the ceiling, the roof trusses and the roof itself.
![]() |
| Ladder to the temporary floor in the roof of George Street Chapel. |
![]() |
| Windows removed earlier being worked on on the temporary floor in the roof of George Street Chapel. |
Friday, 22 February 2013
Day 15 - Windows - Lambert Walker Team - Peter and Plasterwork
Week 3 - Day 15
Summary of the week.
The remaining chapel windows were removed today. A long and tiring job for the team involved, but essential if the scaffolders are to complete the final sections of scaffolding next week. Well done Ian, Chris, Sam and Ali.
Also thanks to Peter Longley, a member of our FOGS group who has been helping with the photographic record.
The removal of the internal plaster has also nearly finished, revealing some interesting things about the construction, alterations and decoration of the chapel over its life-time.
More information on these discoveries next week.
Summary of the week.
The remaining chapel windows were removed today. A long and tiring job for the team involved, but essential if the scaffolders are to complete the final sections of scaffolding next week. Well done Ian, Chris, Sam and Ali.
Also thanks to Peter Longley, a member of our FOGS group who has been helping with the photographic record.
The removal of the internal plaster has also nearly finished, revealing some interesting things about the construction, alterations and decoration of the chapel over its life-time.
More information on these discoveries next week.
![]() |
| George Street Chapel protected by scaffolding and waiting for its roof covering to be completed in Week 4 of the works schedule. |
![]() |
| Window freed and leaning inwards ready for lifting out. |
![]() |
| Window tipped ready for lifting upwards and inwards. |
![]() |
| Lambert Walker Team - Site Manager, Ian Mullin Chris Marshall, Ali Walker, Sam McNamara. |
![]() |
| Peter Longley, FOGS, one of those who is helping keep a photographic record of the works to conserve, repair and adapt George Street Chapel. |
Labels:
FOGS,
lambert walker,
windows
Location:
Oldham, UK
Thursday, 21 February 2013
Day 14 - Removal of Windows
Week 3 - Day 14
The first window frames were removed today.
Hopefully the rest will be removed tomorrow.
There have been some interesting decorations uncovered as the plaster has been removed from the walls.
Photos to be uploaded tomorrow.
The first window frames were removed today.
Hopefully the rest will be removed tomorrow.
There have been some interesting decorations uncovered as the plaster has been removed from the walls.
Photos to be uploaded tomorrow.
![]() |
| The first of the George Street Chapel windows removed for repair and conservation. |
Wednesday, 20 February 2013
Day 13 - Freeing up the Windows