Thursday 7 March 2013

Day 24 - Architects and Contractors Progress Meeting

Week 5 - Day 24
The first progress meeting was held this morning with architects, structural engineer, QS, builders, HLF and AgeUK Oldham.
Meanwhile on site work carried on to repair the windows. De-glazing taking place over the next few days. Also investigations to the supporting brick pillars in the cellar and the pointing on the outside walls as well as the removal of all the roofing slates. The slates are very thin and the nails have become loose. The schedule of works includes the provision for new felt and slates in correct period slates to give the roof a chance for another 200 life.

John Prichard explains work to refurbish windows
on the temporary floor in the roof of George Street Chapel.

Carefully removing slates.
All slates removed from the rear side of the roof at George Street Chapel.

No comments:

Post a Comment