Monday 4 March 2013

Day 21 - Completion of Enclosure around Chapel

Week 5 - Day 21
The envelope that will protect George Street Chapel was completed today. This will allow work to continue even during bad weather whilst the slates and lath and plaster ceiling are removed and then rebuilt.
This photo was taken from the top floor of Spindles car park.
George Street Chapel completely enclosed
to protect the chapel from the weather once the roof is dismantled.




No comments:

Post a Comment