Week 22 - Day 104
The original floorboards are being replaced around the opening made for the new stairwell and lift.
Information posted by the Friends of George Street about events and activities at the former Independent Methodist Chapel at George Street, Oldham by Age UK Oldham. The early posts describe the works to conserve, restore and adapt this Grade ll* Listed Building betwee 2012-13. Restoration works were supported by a grant from the HLF, with match funding from the Andrew Lloyd Webber Challenge Fund, English Heritage and the Architectural Heritage Fund as well as Viridor Credits and Lloyds Bank.
Monday, 8 July 2013
Sunday, 7 July 2013
Update on Restoration of the George Street Chapel Pipe Organ - July 2013
Yvonne Lee, CEO Oldham Age Concern and Maggie Hurley, Community Development Officer visit David Wood Organ Builders on 3rd July to see how the restoration was going of the pipe organ from George Street Chapel.
Friday, 5 July 2013
Day 103 - Tilt Fillet
Week 21 - Day 103
Timber arrived today to enable the fitting of a tilt fillet at the end of the rafters. This will help to stop rainwater from running back behind the last slate, and spill water into the gutter.
Timber arrived today to enable the fitting of a tilt fillet at the end of the rafters. This will help to stop rainwater from running back behind the last slate, and spill water into the gutter.
Thursday, 4 July 2013
Day 102 - Lift
Week 21 - Day 102
Is this half up or half down?
The lift emerges at the chapel floor. It can be seen in the photo below, but eventually will be hidden from the main chapel floor behind a partition, so this modern insertion will not be visible from the chapel area.
Is this half up or half down?
The lift emerges at the chapel floor. It can be seen in the photo below, but eventually will be hidden from the main chapel floor behind a partition, so this modern insertion will not be visible from the chapel area.
Wednesday, 3 July 2013
Day 101 - Construction of Platform Lift
Week 21 - Day 101
The construction of the platform lift has now started. The framework has been erected, rising from the concrete base in the cellar and rising to the chapel floor. The platform lift has been purchased from Stannah.
The construction of the platform lift has now started. The framework has been erected, rising from the concrete base in the cellar and rising to the chapel floor. The platform lift has been purchased from Stannah.
Tuesday, 2 July 2013
Day 100 - New Brickwork behind New Stone Gutter